Construction is proposed to begin on Monday, October 26, 2026 and will start with installation of a sound wall for noise mitigation along the south edge of the site, facing Ayres Avenue. Work will then move to interior and roof demolition to create new floor slab openings for utility shafts and interior stairs; installation of steel at new floor openings; disconnecting, rerouting or removing utilities; installation of scaffolding; site excavation and shoring; tree and site paving removal. 

This page will be updated monthly with forthcoming construction activities. 

For any construction-related concerns, please email us: ResearchPark@capnet.ucla.edu

Construction work is scheduled Monday-Friday, 7am – 5 pm. 

UCLA Research Park East Project

Impact Schedule

The following table outlines construction activities that are anticipated to occur at the UCLA Research Park East project from October 26, 2026 to December 31, 2027*

 

ActivityLocationDescriptionAnticipated StartAnticipated CompletionNoise LevelDust LevelTraffic
Site MobilizationResearch Park East & WestStart of construction, contractors starting on-site. Parking in Research Park West10/26/2026On-GoingLowLowModerate
Site MobilizationRPE South LotSite set up including deliveries of general materials, trailer, disposal bins, etc.10/26/2026On-GoingLowLowModerate
Site MobilizationRPE South LotInstallation of sound wall10/26/202611/20/2026MediumLowLow
Site MobilizationRPE South LotInstallation of sound blankets10/26/202611/20/2026MediumLowLow
DemolitionRPE RoofSaw-cutting of concrete roof deck on top of Research Park East11/2/20262/2/2027MediumLowLow
Site ImprovementsRPE South LotSite demolition including landscaping, hardscaping and grading activities11/2/202612/30/2027LowMediumLow

 